I have two cross-sectional series country and sector in my data. The sector is under country. When I try to import the data into eviews workfile, eviews does not recoginize it as panel data (No Panel Options in Equation Estimation). How to fix this problem?
Thanks in advance for posting answer.
A quick reply is appreciated.
how to import 'panel under panel' data?
Moderators: EViews Gareth, EViews Steve, EViews Moderator, EViews Jason
-
ivansy0727
- Posts: 1
- Joined: Thu Aug 14, 2014 5:15 am
how to import 'panel under panel' data?
- Attachments
-
- data2.xlsx
- (277.57 KiB) Downloaded 210 times
-
EViews Gareth
- Fe ddaethom, fe welon, fe amcangyfrifon
- Posts: 13604
- Joined: Tue Sep 16, 2008 5:38 pm
Re: how to import 'panel under panel' data?
You have a 3D panel (time and two cross-section IDs). You can structure your page as a panel by clicking on Proc->Structure/Resize Current Page, then changing the structure to Dated Panel, entering you two cross-section series in the cross-section IDs, and your date series in the time id.
However, EViews doesn't offer panel estimation options when working in a 3d panel.
However, EViews doesn't offer panel estimation options when working in a 3d panel.
Who is online