I am attempting to copy data from one workfile to another.

The source workfile has an irregular date format and the target is a regular five day week format.

I want to copy the data from the source to the target so that it fills target workfile with the source data only on the dates in the source, leaving the rest as NA. I will then recode out the nas.

It works in all the workfile pages other than one, where it fills the data down between dates. I can't figure out why.

Any advice?

Re: Copying series between two workfiles

Posted: Thu Dec 29, 2016 10:01 pm
by JimForest
It appears I found the answer by adjusting the frequency conversion method. Not sure what I did for one page to behave differently, but it appears to be solved.